KLIA2 - 212 NCR on UEM- Bina Puri

the star biz 24 Jun 2013
It was reported that MAHB, Malaysian Airport Holding had submitted a total of 212 non-compliance reports against the contractors of KLIA2. The defects have to be rectified before the opening on 30 Apr 2014.

For now the UEM Bina Puri has been slapped with RM6mil monthly fine. With the handling over in on Apr 31, the fine will be for 318 days from the original date on Jun 16 2013, and with charges of rm199,445.40, the total fine will be rm63.42mil.

UEM won the contract to build up the KLIA2 for rm997.2 mil in 2010. The new revised budget to complete the airport is RM4billion.  