Fiasco in the KLIA is nothing new. When the airport opened on 27 June 1998 a week before the Hong Kong's opening. The truth was, the airport was not ready. That time I was still working with MAS, and spent weeks in KLIA, doing the volunteer jobs to help ease up the system. The gate allocation system did not work yet. So yo can find pilots were looking around for their aircraft. The airlines staff were having problem to identify which aircraft were for which flight.
The bag tagging and sorting system did not work. The aircraft departs without the bags. You can find thousands of passengers bags laying to be identified.
In most countries that care for safety and passengers comforts, rather that records of achievements, would not open such airport.
AIR ASIA
- Urge the government to set up independent body to probe the delays.
- The airline alleged that the cost could be in term of 5billions.
- Dismissed the claim that the delay due to the airlines slow decision on the baggage handling system.
MALAYSIAN AIRPORTs
- Slapped LAD totaling rm63.42mil
- Cost capped to rm4bil
BINA PURI - Part of UEM Group with possible link to UMNO.
- appealing against the LAD
- Delays were caused by last minutes decision by MAHB
- 93% of the jobs have been completed and the remaining 7% by end of this year.